Settling a housing disrepair claim does not always mean the financial dispute is over.

For housing associations, local authorities and their defendant solicitors, the next challenge is often the claimant's legal costs. A relatively modest disrepair claim can be followed by a substantial Bill of Costs, sometimes involving hourly rates, time spent and disbursements that appear difficult to justify.


The question is not simply whether the bill looks excessive. It is what the paying party can properly challenge, what a reasonable settlement might be and how to resolve the costs dispute without unnecessary further expense.


At SPH Costs, we assist housing providers and defendant legal teams with precisely these issues, from the initial review of a claimant's costs claim through to negotiation, settlement and, where necessary, detailed assessment.


1. Check what costs the Claimant is actually entitled to recover


Before examining individual entries in a Bill of Costs, the starting point should be the legal basis of the claimant's entitlement. Consider:


  • What does the court order or settlement agreement say about costs?

  • Does the entitlement cover the entire claim or only particular issues or periods?

  • Was the matter concluded by a court order, Part 36 acceptance or another form of settlement?

  • Are fixed recoverable costs applicable, or are costs subject to assessment?

  • Are there any issues concerning discontinuance, allocation, conduct or the scope of the costs order?


These questions matter because a paying party should not begin negotiating individual time entries without first understanding the proper scope of the costs claim.

The amount claimed in a bill is not necessarily the amount legally recoverable.


2. Do not confuse an informal costs claim with formal detailed assessment proceedings


Housing disrepair costs claims are often presented informally after settlement, with claimant solicitors inviting the defendant to agree a figure. An informal Bill of Costs can provide an opportunity to negotiate before formal assessment proceedings begin.

However, the position changes where the receiving party serves a Notice of Commencement of Detailed Assessment Proceedings, accompanied by the relevant Bill of Costs.


Under CPR 47.9, the usual period for serving Points of Dispute is 21 days after service of the Notice of Commencement.

Missing the applicable deadline can expose the paying party to an application for a Default Costs Certificate. It is therefore essential to identify whether the bill has merely been sent for negotiation or whether formal proceedings have commenced.

If formal assessment papers have been served, the deadline should be checked immediately.


3. Identify where the costs may be excessive


A proper bill review goes beyond applying a percentage reduction to the total claimed.

Depending on the circumstances, potentially contentious areas in housing disrepair costs include:


Solicitors' hourly rates

The rates claimed should be considered against the applicable principles of reasonableness, the nature of the work and the experience reasonably required.

A claim for work at a senior fee earner's rate does not automatically establish that senior-level involvement was reasonably necessary throughout the matter.


Excessive or duplicated time

A bill may contain significant time for reviewing documents, internal discussions, correspondence, drafting or repeated consideration of the same issues. The important question is whether the work and time claimed were reasonably incurred and reasonable in amount, having regard to the actual requirements of the case.


Expert and surveyor costs

Housing disrepair matters frequently involve inspection reports, schedules of works and expert evidence. Expert fees and associated work should be examined against the issues genuinely in dispute, the work reasonably required and the relevant procedural position.


Costs disproportionate to the dispute

Where standard-basis assessment applies, proportionality is an important consideration under CPR 44.3. However, a high bill relative to the damages alone does not automatically make the entire claim irrecoverable. The court must consider the relevant circumstances and the applicable costs regime.


Work undertaken after the dispute could have been resolved


The chronology may also matter. Offers of repair, access arrangements, expert evidence, settlement proposals and the parties' conduct can all provide useful context when examining the necessity and reasonableness of particular work. Each objection must be supported by the facts and the applicable legal principles. A general assertion that a bill is excessive is rarely enough.


4. Establish a realistic settlement bracket before negotiating


One of the most useful outcomes of an initial costs review is a practical assessment of settlement value. Rather than simply telling the housing association that a bill is too high, a specialist costs review should aim to establish:


  • The principal points of challenge.

  • The strengths and weaknesses of the paying party's position.

  • A realistic settlement bracket.

  • The likely cost and risk of taking the dispute further.

  • Whether early negotiation represents the most commercially sensible option.


For housing providers dealing with numerous disrepair matters, this approach can be particularly valuable. It allows the organisation to make an informed decision about settlement authority and potential exposure without becoming unnecessarily involved in every stage of negotiation.


The objective is not to secure the largest possible headline reduction at any cost. It is to achieve a defensible, commercially sensible outcome.


5. Consider whether the costs dispute can be managed externally


An in-house litigation team may have successfully defended or settled the underlying disrepair claim but still face considerable work resolving the claimant's legal costs. That work can involve reviewing lengthy bills, preparing settlement advice, exchanging offers, challenging individual items and monitoring procedural deadlines. For housing associations and local authorities managing a portfolio of claims, the cumulative burden can be substantial. A managed paying-party costs service can reduce that workload. At SPH Costs, our approach can include:


  1. Reviewing the claimant's bill and the relevant case papers.

  2. Identifying recoverability, reasonableness and proportionality issues.

  3. Advising on an appropriate negotiation bracket.

  4. Agreeing settlement authority with the instructing client.

  5. Conducting negotiations directly within that agreed authority.

  6. Escalating matters requiring Points of Dispute, provisional assessment or detailed assessment, as appropriate.


This provides a structured process while leaving the client in control of the overall settlement parameters.


6. Know when to negotiate and when to proceed to detailed assessment


Not every disputed housing disrepair bill requires a contested assessment hearing.

In many cases, a carefully prepared initial review and reasoned negotiation can lead to agreement without the additional cost and time associated with formal proceedings.

Other cases may involve genuine disputes over entitlement, procedural matters, hourly rates, expert fees or substantial items of work that cannot be resolved by negotiation alone. Where detailed assessment proceedings are necessary, the paying party may require specialist Points of Dispute, advice on offers and representation by an appropriately qualified Costs Lawyer. The decision should be proportionate to the financial issues and litigation risk involved.


7. A practical checklist for housing associations and defendant solicitors


When a claimant's housing disrepair costs bill arrives:

  • Establish the costs entitlement. Check the order or settlement terms before considering the amount claimed.

  • Identify any deadline. Confirm whether formal detailed assessment proceedings have commenced.

  • Retain the key documents. These may include pleadings, settlement correspondence, offers, relevant orders, expert reports and the bill itself.

  • Obtain a specialist review. Identify realistic areas of challenge rather than relying on an arbitrary percentage reduction.

  • Agree a settlement strategy. Set a reasonable negotiation bracket and clear authority.

  • Escalate only where justified. Consider the likely costs, benefits and risks of detailed assessment.


For housing providers dealing with recurring disrepair claims, adopting a consistent approach to costs review and settlement can also improve internal reporting and reduce avoidable demands on legal teams.


Specialist housing disrepair costs defence from SPH Costs


SPH Costs provides managed paying-party legal costs defence for housing associations, local authorities and defendant solicitors throughout England and Wales.


We assist with informal costs claims, Bill of Costs reviews, settlement advice, negotiations, Points of Dispute and detailed assessment proceedings. Our service is designed to take the day-to-day management of costs negotiations away from busy legal teams, while ensuring that settlement decisions remain within agreed client authority.


Received a claimant solicitor's Bill of Costs following a housing disrepair claim?

Find out how SPH Costs can assist with reviewing, challenging and negotiating the amount claimed.



Alternatively, contact SPH Costs to discuss a particular bill or ongoing costs defence support.


This article provides general information about legal costs procedure in England and Wales. The applicable costs regime, recoverability and procedural requirements depend on the circumstances of the individual matter.

 
 

Search

Disclaimer

The content of this blog is provided for general information purposes only and does not constitute legal advice. The views expressed are those of SPH Costing Services Ltd and do not necessarily reflect the views of any instructing solicitor or client. No reliance should be placed on this content in relation to any specific matter, and independent legal advice should always be sought. SPH Costing Services Ltd accepts no liability for any loss or consequence arising from reliance on the information published.

bottom of page