top of page

Delay in Detailed Assessment Proceedings | CPR 47.8 Explained

  • Jun 25, 2015
  • 3 min read

Updated: Jan 30


Delay in Starting Detailed Assessment Proceedings


Delays in commencing or progressing detailed assessment procedure can create serious procedural consequences under CPR Part 47. A receiving party who fails to progress costs assessment promptly may face challenges based on delay, proportionality, and case management powers. CPR 47.8 and related provisions give the court wide discretion where assessment proceedings are not pursued in a timely way.


What Are the Risks of Delay Under CPR 47.8?


  • The court may refuse to allow the assessment to proceed

  • Costs may be reduced due to procedural inefficiency

  • Relief from sanctions may be required

  • Paying parties may argue prejudice and abuse of process


How Courts Approach Delay in Costs Assessment


Courts consider:

  • Length of delay

  • Reasons for delay

  • Prejudice to the paying party

  • Whether proceedings were pursued with diligence

  • Overall proportionality of further assessment


These issues are commonley handled by costs lawyers regulated by the CLSB, who understand how procedural delay arguments are deployed in practice.



We find that one of the most common reasons for enquiries from potential new clients is dissatisfaction with their existing draftsmen due to delays. Our service standard of a 7 days turnaround for producing Bills of Costs is a significant factor in us receiving new instructions.


These days, most Solicitors are far more aware of the need to run a tight ship than they were in days past. Simply sitting on an entitlement to costs is not an option, particularly, where the Solicitor is only going to get paid from the money recovered from the opponent as opposed to the client paying as the case goes along. However, there are still cases of apparently “inordinate and inexcusable delay” which lead to applications under CPR part 47.8. Under CPR 47.7, the period for commencing Detailed Assessment proceedings (i.e. formally serving the Bill of Costs under a Notice of Commencement) is three months from the date of the Order. At the expiry of that time the paying party may make an application for an unless Order requiring the proceedings to be commenced within a specified period (47.8). The costs of that application will generally follow the event and the Order will normally specify that the costs will be allowed at nil unless there is compliance with its terms.

The ACL Newsletter of 18th June 2015 carried a report of a case on Lawtel of F N & Another v Secretary of State for the Home Department where such an application had been made. Whilst there were other arguments deployed, principally the receiving party maintained that they had indicated to the paying party that it would normally take 6 to 8 weeks to commence Assessment proceedings. In that particular case, the three month period under 47.7 had long expired and the comment as to the likely time to be taken was made in response to a threat of an application. In these post Denton days, it is very clear that the Court do require the parties to demonstrate a reasonable approach to questions of default and it does seem here that the Judge felt that the application should have been avoided if the receiving party had made a more formal request for an extension of time. The application was issued 7 weeks after the receiving party’s indication of the likely timescale. On Appeal, the Court found that the application had been reasonably made and therefore costs followed the event. However, we do think it is this point over appropriate communication in the face of a threat of an application which is the most critical point. If there is some difficulty then this should be fully and openly explained to the opponent and (here) the receiving party should use its best endeavours to comply with any extension that has been requested. It seems fairly clear that the approach of the Courts is not that Rules are to be absolutely enforced as appear to be the case post Mitchell. However, they do retain considerable importance and cannot be simply ignored. A proactive approach will however most likely meet with the Courts approbation.


FAQs on Delay in Detailed Assessment


Q: Can delay stop a detailed assessment? Yes. Excessive or unexplained delay can lead to case management sanctions or refusal to allow assessment to proceed. Understanding the distinction between costs lawyer vs costs draftsman roles can alos affect how delay arguments are advanced.

Q: Does CPR 47.8 impose a time limit? It gives the court procedural control where assessment is not progressed promptly.

Q: Can a party seek relief from sanctions? Yes, but the court will consider delay, explanation, and prejudice.

 
 

Disclaimer

The content of this blog is provided for general information purposes only and does not constitute legal advice. The views expressed are those of SPH Costing Services Ltd and do not necessarily reflect the views of any instructing solicitor or client. No reliance should be placed on this content in relation to any specific matter, and independent legal advice should always be sought. SPH Costing Services Ltd accepts no liability for any loss or consequence arising from reliance on the information published.

bottom of page